My First RCA

Client:

I had been working within the Manufacturing Technology team on site and was studying the Pareto of top ten production losses due to equipment failures.

Within the top ten was a critical centrifugal pump that had contributed to 88 hours lost production over the previous 16 months.

Operating Context:

The pump was required to operate 24/7, however, it was not continually pumping to production but was required to run through a kickback line. The nature of the product being pumped meant steam jacketed pipework was required to keep the product in solution.

A design change had been implemented the previous year which included a new 3 way valve which allowed switch over from production flow to kickback using automated control. A new design double cartridge seal was also installed on the pump complete with steam flush.

 

Key Findings:

I first facilitated RCA in 1997 and became an accredited global trainer. At PRS, we support 5 Whys, Causal Factor, and Apollo methodologies. Contact us for RCA support or training.

Equipment Reliability
Breaking Records Together – Operational and Reliability Excellence
Learn More
Maintenance Strategy
Development of Maintenance Strategies for Food Grade Oil Facility
Learn More
Root Cause
My First RCA
Learn More